On the workflow board it is great to capture day to day tasks and their time taken, however, we would like to assign an expected timeline for completion for each of the tasks to build a gantt style chart to allow project forecasting. Is this something that Factory has implemented?
This can be roughly done in the planner but will be limited and a bit chaotic. It would be great to have a standalone chart to allow us to identify or roadmap future projects and identify any clashes and restraints prior.
Features:
- It would be great to be able to drive the gantt chart dates from project tasks on the workflow page or similar
- as well as allowing editing if there are stoppages to work etc.
- set up each project with the subheadings similar to our headings and be able to assign a start / end date, Assignee, status
E.G.
Project - Smiths Builders
Sub Items:
Tender - Quotation (2 Weeks)
Preliminary Design (1 Week)
Manufacture Drawing / Engineering ( 2 Week)
Material Procurement (2 Week)
Fabrication (1 Week)
Powder Coat / Paint (1 Week)
Delivery & Install (1 Week)